Individual performance reports for 2026-05-01 to 2026-05-31
Alex Delgado
adelgado@assemblestudio.com Project Management | Production
33.9% Delivery (Adj.)
?Delivery as % of logged hours excluding 16h PTO. Raw: 30.7%. = delivery / (logged - PTO)
94.4% Adj. Utilization
?Delivery + productive internal hours as % of logged hours (excl. PTO). = (delivery + internal) / (logged − PTO)
33 Projects
15.1% PM Overhead
?PM hours as a percentage of total project hours. Lower means more leverage. Target: <15%. = PM hrs / total hrs
3 Over 10 Close to Limit 20 Healthy 0 No Budget
Catalina Peña
cpena@assemblestudio.com Creative | Production
66.0% Delivery (Adj.)
?Delivery as % of logged hours excluding 0h PTO. Raw: 66.0%. = delivery / (logged - PTO)
96.3% Adj. Utilization
?Delivery + productive internal hours as % of logged hours (excl. PTO). = (delivery + internal) / (logged − PTO)
24 Projects
6 Banners2 Design1 Video
Devani Genardi
dgenardi@assemblestudio.com Development | DPDevelopment | WebTechnical Lead
80.6% Delivery (Adj.)
?Delivery as % of logged hours excluding 16h PTO. Raw: 72.9%. = delivery / (logged - PTO)
90.8% Adj. Utilization
?Delivery + productive internal hours as % of logged hours (excl. PTO). = (delivery + internal) / (logged − PTO)
26 Projects
9 Emails8 Banners
Dionicio Taylor
dtaylor@assemblestudio.com Development | DPDevelopment | FullStackDevelopment | Web
55.2% Delivery (Adj.)
?Delivery as % of logged hours excluding 0h PTO. Raw: 55.2%. = delivery / (logged - PTO)
100.0% Adj. Utilization
?Delivery + productive internal hours as % of logged hours (excl. PTO). = (delivery + internal) / (logged − PTO)
12 Projects
3 Emails4 Web
Gabriela Uzcategui
guzcategui@assemblestudio.com Project Management | Production
58.9% Delivery (Adj.)
?Delivery as % of logged hours excluding 10h PTO. Raw: 55.4%. = delivery / (logged - PTO)
93.8% Adj. Utilization
?Delivery + productive internal hours as % of logged hours (excl. PTO). = (delivery + internal) / (logged − PTO)
41 Projects
24.8% PM Overhead
?PM hours as a percentage of total project hours. Lower means more leverage. Target: <15%. = PM hrs / total hrs
14 Over 7 Close to Limit 20 Healthy 0 No Budget
Jimmy Gonzalez
jgonzalez@assemblestudio.com Development | DPDevelopment | WebTechnical Lead
84.8% Delivery (Adj.)
?Delivery as % of logged hours excluding 8h PTO. Raw: 80.8%. = delivery / (logged - PTO)
97.5% Adj. Utilization
?Delivery + productive internal hours as % of logged hours (excl. PTO). = (delivery + internal) / (logged − PTO)
28 Projects
17 Emails5 Banners1 Web
Jose Montealegre
jmontealegre@assemblestudio.com Project Management | Technical
39.9% Delivery (Adj.)
?Delivery as % of logged hours excluding 12h PTO. Raw: 37.1%. = delivery / (logged - PTO)
100.0% Adj. Utilization
?Delivery + productive internal hours as % of logged hours (excl. PTO). = (delivery + internal) / (logged − PTO)
5 Projects
15.1% PM Overhead
?PM hours as a percentage of total project hours. Lower means more leverage. Target: <15%. = PM hrs / total hrs
0 Over 1 Close to Limit 4 Healthy 0 No Budget
Laura Melissa Gomez
lgomez@assemblestudio.com QA | Creative
69.9% Delivery (Adj.)
?Delivery as % of logged hours excluding 0h PTO. Raw: 69.9%. = delivery / (logged - PTO)
100.0% Adj. Utilization
?Delivery + productive internal hours as % of logged hours (excl. PTO). = (delivery + internal) / (logged − PTO)
49 Projects
18 Emails12 Banners1 Design1 Video
Mari Mora
mmora@assemblestudio.com Creative | ProductionCreative | UX/UICreative ManagerProject Management | CreativeQA | Creative
51.8% Delivery (Adj.)
?Delivery as % of logged hours excluding 16h PTO. Raw: 46.9%. = delivery / (logged - PTO)
91.3% Adj. Utilization
?Delivery + productive internal hours as % of logged hours (excl. PTO). = (delivery + internal) / (logged − PTO)
17 Projects
4 Banners1 Design
Freelancers 1
External resources — excluded from studio KPIs