Assemble Assemble Performance
Snapshots / 2026-04-14-001951 / Clients / Broadview Labs

Broadview Labs

2026-03-01 to 2026-03-31

46.25h Total Hours
7 Projects
1.12x Budget Efficiency
5 Team Members
29.2% PM Overhead 13.5h of 46.25h
14.1% QA Effort 6.5h of 46.25h
17.7% PM/Dev Ratio 65.5h PM / 370.5h total
$19,664 Revenue Invoiced $13,638 collected

Hours by Department

Development
25.5h (1 projects)
Digital Production
20.75h (3 projects)

Team

Jimmy Gonzalez DEV
26.25h
Alex Delgado PM
8h
Jose Montealegre PM
5.5h
Luis Xatruch FREELANCEQA
4h
Laura Melissa Gomez QACREATIVE
2.5h

Financial Health

4 Over 2 At Risk 1 Healthy
7 projects 328h budgeted / 367.5h actual Efficiency: 1.12x

Over Budget (4)

Project Dept Budget Spent Over % Used
bvl-rel-3901 RELISTOR Post-visit Form RTE prod 14h 50.25h 36.25h 358.9%
bvl-xfx-3905 Xifaxan Coverage Resources RTE prod 11.25h 18.25h 7h 162.2%
bvl-xfx-3876 BH Veeva RTE Emails prod 35.25h 41.25h 6h 117%
bvl-xfx-3821 Xifaxan iVA CLM Updates dev 131h 151.75h 20.75h 115.8%

At Risk (2)

Project Dept Budget Spent Remaining % Used
bvl-xfx-3851 Xifaxan iVA CLM Tracking - ClickStream Tagging dev 43h 40.25h 2.75h 93.6%
bvl-xfx-3909 Xifaxan - RTE Filtering Feature dev 65h 56.5h 8.5h 86.9%

Healthy (1)

Project Dept Budget Spent Remaining % Used
bvl-xfx-3847 Xifaxan iVA GI CLM Updates dev 28.5h 9.25h 19.25h 32.5%