Broadview Labs
2026-07-01 to 2026-07-31
90h Total Hours
19 Projects
0.51x Budget Efficiency
7 Team Members
26.1% PM Overhead 23.5h of 90h
6.7% QA Effort 6h of 90h
$17,797 Revenue Invoiced $5,225 collected
Hours by Department
Team
Financial Health
1 Over 5 Close to Limit 13 Healthy
19 projects 691.75h budgeted / 352.25h actual Efficiency: 0.51x
Over Budget (1)
| Project | Dept | Budget | Spent | Over | % Used | State |
|---|---|---|---|---|---|---|
| bvl-wxl-4064 Wellbutrin RTE Updates Priority 1 and 2 | prod | 35.5h | 51.5h | 16h | 145.1% | Active |
Close to Limit (5)
| Project | Dept | Budget | Spent | Remaining | % Used | State |
|---|---|---|---|---|---|---|
| bvl-xfx-4004 CLM with Video Demo | dev | 4h | 4h | 0h | 100% | Active |
| bvl-4258 Xifaxan IBDS - PCP GI updates | dev | 10h | 9.5h | 0.5h | 95% | Active |
| bvl-xfx-3851 Xifaxan iVA CLM Tracking - ClickStream Tagging | dev | 43h | 40.25h | 2.75h | 93.6% | Active |
| bvl-bau-4236 SLQ AI Updates research | dev | 11h | 9.5h | 1.5h | 86.4% | Active |
| bvl-4287 XIFAXAN CABTREO TOGGLE | dev | 12h | 9.75h | 2.25h | 81.3% | Active |