Assemble Assemble Performance
Snapshots / 2026-01-31-235959 / Clients / Petauri MAx

Petauri MAx

2026-01-01 to 2026-01-31

32h Total Hours
6 Projects
0.78x Budget Efficiency
3 Team Members
35.9% PM Overhead 11.5h of 32h
9.4% QA Effort 3h of 32h
20.9% PM/Dev Ratio 28h PM / 134h total

Team

Devani Genardi DEV
17.5h
Jose Montealegre PM
11.5h
Luis Xatruch FREELANCEQA
3h

Financial Health

2 Over 1 At Risk 3 Healthy
6 projects 168.75h budgeted / 131.5h actual Efficiency: 0.78x

Over Budget (2)

Project Dept Budget Spent Over % Used
pmax-cel-3889 Yuflyma Site Removal dev 4h 7.5h 3.5h 187.5%
pmax-cel-3873 Celltrion Connect - Osenvlet PI update dev 3.75h 5.5h 1.75h 146.7%

At Risk (1)

Project Dept Budget Spent Remaining % Used
pmax-cel-3869 Celltrion Connect - Adalimumab Updates dev 43h 35.75h 7.25h 83.1%

Healthy (3)

Project Dept Budget Spent Remaining % Used
pmax-cel-3796 Vegzelma Landing Page dev 44h 34.25h 9.75h 77.8%
pmax-cel-3825 Avtozma Injection Support And December Changes dev 56h 41.5h 14.5h 74.1%
pmax-neu-3856 CFT Market Access Minutes Issue 3 Email prod 18h 7h 11h 38.9%